Facts

  • The Public Service Company of New Mexico (PNM) sought approval from the New Mexico Public Regulation Commission (Commission) to abandon its partial ownership in the Four Corners Power Plant and to issue energy transition bonds to cover the costs of this abandonment under the Energy Transition Act (ETA). The Commission denied PNM's application, leading to PNM's appeal to the Supreme Court of the State of New Mexico (paras 1-2, 5).

Procedural History

  • [Not applicable or not found]

Parties' Submissions

  • Appellant (PNM): Argued that the Commission erred in denying the application for abandonment because PNM had identified adequate potential new resources to provide reasonable service to retail customers, as required by the ETA. PNM also contested the Commission's reliance on the lack of exit scenario modeling and the deferral of issues related to PNM's prior investments in the Four Corners Plant (para 2).
  • Appellee (Commission): Maintained that PNM's application failed to meet the requirements of the ETA because it did not identify adequate potential new resources with sufficient detail and relied on generic placeholders instead of actual resources under consideration. The Commission also raised concerns about supply chain issues affecting the timeliness of new resource deployment (paras 12, 26).
  • Intervenors-Appellees: Their specific arguments are not detailed in the decision.

Legal Issues

  • Whether the Commission's denial of PNM's application for abandonment was arbitrary and capricious, not supported by substantial evidence, outside the scope of the agency’s authority, or otherwise inconsistent with law (para 3).
  • Whether PNM's identification of potential new resources met the requirements of Section 62-18-4(D) of the ETA (paras 13-21).
  • Whether the Commission's decision was supported by substantial evidence (paras 22-26).
  • Whether the Commission's decision was arbitrary and capricious (paras 27-30).

Disposition

  • The Supreme Court affirmed the Commission's final order denying PNM's application for abandonment of the Four Corners Power Plant and issuance of a financing order for energy transition bonds (para 31).

Reasons

  • The Supreme Court, with Justice Zamora writing and Justices Bacon, Vigil, Thomson, and Vargas concurring, held that the Commission's decision was not arbitrary and capricious, was supported by substantial evidence, and was consistent with the law. The Court found that PNM did not meet its burden under Section 62-18-4(D) of the ETA because it failed to identify adequate potential new resources with sufficient detail, relying instead on generic placeholders and prior bids for other projects. The Court also noted that the Commission's requirement for PNM to provide more detailed information about potential new resources was reasonable and within its authority, given the factual determinations and policy issues involved. The Court deferred to the Commission's expertise in determining the sufficiency of PNM's application and found no error in the Commission's decision to defer final resolution on issues related to PNM's prior investments in the Four Corners Plant (paras 13-30).