Facts

The Human Services Department (HSD) issued a Request for Proposals (RFP) to lease office space in Santa Fe. The Plaintiff submitted a proposal, which was ranked first by the Selection Committee. However, HSD informed the Plaintiff that General Services Department (GSD) approval and legislative appropriation were required before a lease could be finalized. After over eight months of uncertainty, HSD canceled the RFP, citing the best interests of the Department. The Plaintiff sought damages for breach of contract or, alternatively, on the basis of estoppel (paras 1-8).

Procedural History

  • Trial court: Held that no contract was formed between the Plaintiff and HSD and denied the Plaintiff's claim for reliance damages (paras 9-10).

Parties' Submissions

  • Plaintiff-Appellant: Argued that a contract was formed when HSD selected the Plaintiff's proposal and that the Plaintiff was entitled to damages for breach of contract or, alternatively, reliance damages under the doctrine of estoppel (paras 11, 16).
  • Defendants-Appellees: Contended that no contract was formed because GSD approval and legislative appropriation were conditions precedent to contract formation. They also argued that estoppel did not apply because the Plaintiff was aware of these conditions (paras 13, 16-17).

Legal Issues

  • Was a contract formed between the Plaintiff and HSD when the Plaintiff's proposal was selected?
  • Should the doctrine of estoppel apply to award the Plaintiff reliance damages?

Disposition

  • The Supreme Court of New Mexico affirmed the trial court's decision, holding that no contract was formed and that the Plaintiff was not entitled to reliance damages under the doctrine of estoppel (paras 19-20).

Reasons

Per Franchini CJ (McKinnon J and Pope J concurring):

  • Contract Formation: The Court held that no contract was formed because GSD approval and legislative appropriation were explicitly stated as conditions precedent to contract formation. The letters sent to the Plaintiff by HSD did not constitute acceptance of the Plaintiff's offer but rather indicated that finalization of the lease was contingent on these conditions. The Court distinguished this case from prior precedent, emphasizing that the conditions in this case were not mere legal formalities but essential prerequisites (paras 13-15).

  • Estoppel: The Court rejected the Plaintiff's estoppel claim, finding that the Plaintiff was at all times aware that HSD's performance was contingent on GSD approval and legislative appropriation. The Plaintiff failed to demonstrate detrimental reliance, as the Plaintiff was informed of these conditions from the outset. The Court also noted that estoppel is rarely applied against the State and only in cases of aggravated or overreaching conduct, which was not present here (paras 16-18).